Deck piers look like a nothing job. A dozen holes, under 2 yards of mud. So crews throw out a price per hole and move on. Say you bid $75 a hole on 12 piers. That is $900. In the example below the job costs you $1,644 to do. You just paid $744 to work a full day. Here is how to bid piers so that does not happen, using 12 piers in 12-inch tubes, 48 inches deep.
Step 1: Count the piers and figure yards
A pier is a round column. The math is 3.14 × radius × radius × depth, all in feet. That gives cubic feet. Divide by 27 for yards. A 12-inch tube has a 0.5 foot radius. 48 inches is 4 feet.
3.14 × 0.5 × 0.5 × 4 = 3.14 cubic feet a pier
3.14 × 12 piers = 37.7 cubic feet ÷ 27 = 1.40 yards
Add 10% so you don't run short. That is 1.54 yards. Order 2.
Pier size, depth, and any wider base at the bottom are set by the plans and your local code. Frost depth is different in every area. Check before you bid.
Step 2: Add up every cost
These are example numbers. Use your own.
| Cost | Amount |
|---|---|
| Concrete, 2 yards at $170 | $340 |
| Short-load fee | $150 |
| Form tubes, 12 at $20 | $240 |
| Rebar and post anchors, 12 at $12 | $144 |
| Auger rental, 1 day | $150 |
| Labor, 2 men × 8 hours × $35 | $560 |
| Fuel and hauling off the dirt | $60 |
| Your total cost | $1,644 |
Step 3: Watch for pier extras
- Short load. Two yards is under the minimum at most plants. Ask what the fee is before you bid. See how to price a small pour.
- Bags or a truck. An 80-pound bag makes about 0.6 cubic feet (check the bag). This job is 37.7 cubic feet, so about 63 bags before any extra. Price the bags and the mixing time against the truck and the fee.
- Rock and roots. One bad hole can eat an hour. Say on the quote what happens if you hit rock.
- Buried lines. Call 811 and get the lines marked before you dig. Plan the wait into your schedule.
- Layout. Piers have to line up with the posts. Stringing and squaring 12 holes takes real time. Put it in your labor hours.
- Inspection. Some towns want to see the holes before you pour. That can mean a second trip.
- Dirt. The dirt from 12 holes has to go somewhere. Spread it on site or haul it, and charge for it.
Step 4: Add your margin
To hit a 25% margin, divide your cost by 0.75.
$1,644 ÷ 0.75 = $2,192
You keep $548. That is $183 a pier, not $75. Most of the cost is the trip, the digging, and the labor. The concrete is the small part.
Pier footing bid calculator
Know your number before you price by the hole.
SlabBid Pro adds up the concrete, digging, labor, and margin from your own prices. Then it sends a clean quote with your logo by text or email. You can look through sample jobs in the app before you start the free trial.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to estimate concrete footings · Concrete short-load fees · How to bid a concrete shed pad