The truck can't back up to a backyard patio. So you call a pump. The pump bill shows up after the pour, and it was never on the bid. In the example below the pump costs $634 on a 7 yard pour. Leave it off and that $634 comes straight out of your profit. Here is how to price a pump into a bid, using a 20 × 24 backyard patio poured 4 inches thick.
Step 1: Figure the yards you will pump
20 × 24 = 480 square feet. Square feet × thickness in inches ÷ 12 ÷ 27 = cubic yards.
480 × 4 ÷ 12 ÷ 27 = 5.93 yards
Add 10% so you don't run short. That is 6.52 yards. Order 7.
Thickness and steel are set by the plans or your local code. The pump company will ask how many yards, how far the hose has to reach, and what mix you ordered. Have those three numbers before you call.
Step 2: Add up every pump charge
Pump companies do not all bill the same way. Most have more than one charge. Ask for all of them. These are example numbers. Use your own.
| Pump charge | Amount |
|---|---|
| Pump time, 3-hour minimum at $150 an hour | $450 |
| Per-yard charge, 7 yards at $4 | $28 |
| Travel and primer for the hose | $100 |
| Pump mix upcharge at the plant, 7 yards at $8 | $56 |
| Your total pump cost | $634 |
That is about $91 a yard on this job. A flat pump bill spread over a small pour is a big number per yard.
Step 3: Watch for pump extras
- Minimum hours. Many pump companies bill a minimum number of hours even if you pour in one. Ask what the minimum is and when the clock starts.
- Waiting. If the truck is late or your crew is not ready, the pump clock may keep running. Have the forms, base, and steel done before the pump shows up.
- Pump mix. A small line pump may need a mix with smaller rock. Ask the pump company what mix it needs, then ask the plant what that mix costs.
- Hose length. A long run around the house may need extra hose. Some companies charge for it. Measure the run and tell them.
- Line pump or boom pump. A boom truck reaches over a house but often costs more than a line pump. Ask which one the job needs.
- Washout. The pump has to wash out somewhere. Pick the spot with the owner before pour day.
- Cancel fee. Ask what it costs if rain moves the pour. Say on the quote who pays if the owner changes the date.
- Wheel it instead. On a short run with a small pour, more men with wheelbarrows may cost less than a pump. Price both ways. See how to figure concrete labor cost.
Step 4: Add your margin
The pump is a cost like any other. It gets your margin too. To hit a 25% margin, divide your cost by 0.75.
$634 ÷ 0.75 = $845
Add $845 to the bid for the pump. Put it on the quote as its own line. Then the customer sees why your price is higher than the guy who forgot it.
Pump cost calculator
Know your full cost before you send the price.
SlabBid Pro adds up the concrete, base, labor, and margin from your own prices. Then it sends a clean quote with your logo by text or email. You can look through sample jobs in the app before you start the free trial.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to bid a concrete patio · Concrete short-load fees · How to bid a concrete driveway apron