Labor is usually the biggest cost you control, and the easiest one to guess wrong. Two mistakes cause most of it: pricing a man at his wage, and guessing the hours instead of counting them.
Step 1: Find your true hourly rate
An hour of labor costs you more than what you pay the man. On top of the wage you pay payroll taxes, workers' comp, unemployment insurance, and often liability insurance that is based on payroll. Ask your accountant or insurance agent what your real add-on is.
$28 wage + 25% add-on = $35.00 an hour
The 25% is an example. Use your own number. Your own hours count too. If you work the job, price your time like a hired hand.
Step 2: Count hours by task
Don't guess the whole job at once. Break it into tasks. Here is an example for an 800 square foot driveway.
| Task | Man-hours |
|---|---|
| Prep and base | 8 |
| Forming | 6 |
| Rebar | 4 |
| Pour and finish (4 men × 3 hours) | 12 |
| Saw cuts and strip forms | 2 |
| Total | 32 |
32 man-hours × $35 = $1,120
Step 3: Add the hours nobody sees
- Drive time. Loading up, driving out, and driving back are paid hours.
- Waiting. A late truck, an inspection, or a slow set can hold a whole crew.
- Trips back. Saw cuts, stripping forms, and sealing often mean a second day on site.
- Weather. Heat speeds up the set and needs more hands. Cold slows finishing.
Step 4: Check your hours after every job
Write down what the job really took. After a few pours you'll have your own hours per square foot, and your bids will get tighter. Then add your margin the right way. See markup vs margin.
Labor cost calculator
Stop guessing your labor.
SlabBid Pro figures labor hours by task from the job you enter, at your own hourly rate. Then it adds materials and margin and sends the quote with your logo.