Thirteen practice problems for concrete estimating. Yards, rebar, gravel, labor, margin, and one full bid. Print it, work it with a pencil, then check the answer key at the bottom. Free for any class or crew.
The answer key prints on its own page, so you can hand out the problems without it.
The rules for this worksheet
- Length × width × thickness (in feet) ÷ 27 = cubic yards. To change inches to feet, divide by 12.
- Round yards to two places. Example: 5.93.
- When a problem says "order," add 10% and round up to the next whole yard.
- All dollar figures are example numbers. On a real job, use your own.
- On a real job, thickness, bar size, and bar spacing come from the plans or your local code.
Part 1: Yards of concrete
1. A slab is 20 feet by 24 feet and 4 inches thick. How many cubic yards is it?
2. Add 10% to your answer from problem 1. How many yards do you order?
3. A driveway is 12 feet by 40 feet and 5 inches thick. How many yards is it, and how many do you order?
4. A footing is 80 feet long, 16 inches wide, and 8 inches deep. How many yards is it, and how many do you order?
5. A wall is 30 feet long, 8 feet tall, and 8 inches thick. How many yards is it, and how many do you order?
6. A round slab is 12 feet across and 4 inches thick. How many yards is it, and how many do you order? (Area of a circle = 3.14 × radius × radius. The radius is half the distance across.)
Part 2: Rebar and gravel
7. A slab is 20 feet by 30 feet. The plans call for bars 24 inches apart both ways. How many feet of bar is that? Add 10% for laps. How many 20-foot sticks do you order?
8. The slab from problem 1 gets a 4-inch gravel base. A cubic yard of this gravel weighs 1.4 tons. Add 10% for packing down. How many tons do you order?
Part 3: Labor and money
9. A pour takes 4 workers 7 hours each. Labor costs $35 an hour. What is the labor cost?
10. A job costs you $3,000. You want a 25% margin. What is your bid, and how much do you keep?
11. The same $3,000 job is marked up 25% instead. What is the bid? What margin is that really?
12. You bid $4,000 on a 20 × 24 slab. What is the price per square foot?
Part 4: A full bid
13. Bid a 24 × 24 garage floor, 4 inches thick. Use these example numbers:
| Cost | Amount |
|---|---|
| Concrete (order with 10% extra) | $170 a yard |
| Gravel, rebar, and forms | $600 |
| Labor, 4 workers × 8 hours | $35 an hour |
| Fuel, blades, sealer | $120 |
Find: yards to order, concrete cost, labor cost, total cost, the bid at a 25% margin, and the price per square foot.
Answer key
1. 20 × 24 × 4 ÷ 12 ÷ 27 = 5.93 yards
2. 5.93 × 1.10 = 6.52. Order 7 yards.
3. 12 × 40 × 5 ÷ 12 ÷ 27 = 7.41 yards. With 10%: 8.15. Order 9.
4. 80 × (16 ÷ 12) × (8 ÷ 12) = 71.11 cubic feet. ÷ 27 = 2.63 yards. With 10%: 2.90. Order 3.
5. 30 × 8 × 8 ÷ 12 ÷ 27 = 5.93 yards. With 10%: 6.52. Order 7.
6. 3.14 × 6 × 6 = 113.04 square feet. × 4 ÷ 12 ÷ 27 = 1.40 yards. With 10%: 1.54. Order 2.
7. 20 ÷ 2 = 10 spaces, so 11 bars × 30 feet = 330 feet. 30 ÷ 2 = 15 spaces, so 16 bars × 20 feet = 320 feet. Total 650 feet. With 10%: 715 feet. 715 ÷ 20 = 35.75. Order 36 sticks.
8. 5.93 yards × 1.4 = 8.30 tons. With 10%: 9.13. Order 10 tons.
9. 4 × 7 × $35 = $980
10. $3,000 ÷ 0.75 = $4,000. You keep $1,000.
11. $3,000 × 1.25 = $3,750. You keep $750. $750 ÷ $3,750 = 20% margin, not 25%.
12. 20 × 24 = 480 square feet. $4,000 ÷ 480 = $8.33 a square foot.
13. 24 × 24 × 4 ÷ 12 ÷ 27 = 7.11 yards. With 10%: 7.82. Order 8. Concrete: 8 × $170 = $1,360. Labor: 4 × 8 × $35 = $1,120. Total cost: $1,360 + $600 + $1,120 + $120 = $3,200. Bid: $3,200 ÷ 0.75 = $4,267. You keep $1,067. 24 × 24 = 576 square feet, so $7.41 a square foot.