Guessing rebar is how a bid comes up short. The fix is simple. Count the bars in each direction, add the laps, and turn it into sticks. Here is the math on a 24 × 30 slab.
Step 1: Count the bars each way
Divide the side by the spacing to get the spaces. Add 1 to get the bars. At 18 inches apart, the spacing is 1.5 feet.
24 ÷ 1.5 = 16 spaces, so 17 bars. Each runs 30 feet. 17 × 30 = 510 feet
30 ÷ 1.5 = 20 spaces, so 21 bars. Each runs 24 feet. 21 × 24 = 504 feet
Total: 1,014 feet of bar.
Step 2: Add for laps
Bars overlap where they meet. That overlap is steel you pay for. Adding 10% covers laps and cut waste on most slabs.
1,014 × 1.10 = 1,115 feet
Step 3: Turn feet into sticks
Rebar is sold in 20-foot sticks at most yards. Divide and round up.
1,115 ÷ 20 = 55.8, so order 56 sticks
At an example price of $9.50 a stick, that is $532. Use your own price.
What tighter spacing costs
Same slab, bars at 12 inches apart.
| Spacing | Bars | Sticks |
|---|---|---|
| 18 inches | 17 + 21 | 56 |
| 12 inches | 25 + 31 | 83 |
Going from 18 to 12 inches adds 27 sticks. That is about half again as much steel, plus the extra hours to tie it. If the plans or the customer change the spacing, change the bid.
Don't forget
- Chairs and tie wire. They are small costs, but they are real. Add them.
- Labor to tie. More bars means more ties. Tighter spacing takes longer.
- Thicker edges and footings. They get their own bars. Count them apart from the slab. See how to estimate concrete footings.
- The plans rule. Bar size and spacing come from the plans or your local code. This page only shows how to count.
Slab rebar calculator
Let the app count the bars.
SlabBid Pro figures the rebar, concrete, forms, and labor from your measurements, then adds your margin. It sends a clean quote with your logo by text or email.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to estimate a concrete slab · How to bid a concrete garage floor · How much gravel under a slab