Concrete is sold by the yard. Gravel is sold by the ton. Mix those up and you order too little base or pay for too much. Here is how to figure the gravel under a 24 × 24 slab with a 4-inch base.
Step 1: Figure cubic yards
Length × width × depth (in inches) ÷ 12 ÷ 27 = cubic yards.
24 × 24 × 4 ÷ 12 ÷ 27 = 7.11 cubic yards
Step 2: Turn yards into tons
A cubic yard of gravel weighs about 1.4 tons. That is a rule of thumb. It changes with the type of rock and how wet it is. Ask your pit for their number.
7.11 × 1.4 = 9.96 tons
Step 3: Add extra for packing down
Gravel packs down when you compact it. Low spots take more than the math shows. Adding 10% covers most jobs.
9.96 × 1.10 = 10.95 tons. Order 11.
Step 4: Price it
These are example numbers. Use your own.
| Cost | Amount |
|---|---|
| Gravel, 11 tons at $25 | $275 |
| Delivery | $120 |
| Base material | $395 |
That is material only. The time to spread it and run the compactor goes on the labor line.
Don't forget
- Soft ground. Wet or soft spots need to be dug out and filled. That takes more rock than a flat 4 inches.
- Grade. If the site is not level, one end of the base is deeper. Measure the deep end, not just the shallow one.
- Truck size. Ask how many tons the truck carries. A second trip for one more ton costs you a second delivery.
- Compactor. If you rent one, put the rental on the bid.
- Dirt hauled out. If you dig down to make room for the base, that dirt has to go somewhere. Price the haul.
Gravel base calculator
Get the base on the bid every time.
SlabBid Pro figures the gravel, concrete, rebar, and labor from your measurements, then adds your margin. It also builds a material list you can send to your supplier.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to bid a concrete garage floor · How much rebar for a slab · How to bid a concrete driveway