Run a yard short on a slab and the crew stands around while you wait on a second truck. Say the short-load fee is $150 and four men wait an hour at $35. That is $290 gone, on example numbers. A missed rebar or base line costs you the same way. Here is how to figure concrete, rebar, base, forms, and labor, using a 24 × 24 garage slab poured 4 inches thick.
1. Concrete
Length × width × thickness (in feet) ÷ 27 = cubic yards. Four inches is 0.333 feet.
24 × 24 × 0.333 ÷ 27 = 7.11 yards
Add 10% so you don't run short. That is 7.82 yards. Order 8.
2. Rebar
Say the rebar goes 18 inches apart, both ways. That is 1.5 feet.
24 ÷ 1.5 = 16 spaces, so 17 bars each way
17 bars × 24 feet × 2 directions = 816 feet
Add 10% for laps. That is about 898 feet, or 45 sticks of 20-foot bar.
3. Gravel base
A 4-inch base under this slab is the same math as the concrete. About 7 yards of gravel. Ask your pit how many tons that is for their rock.
4. Forms
If the slab needs forms, measure the outside edge. Here that is 24 × 4 = 96 feet of form boards, plus stakes.
5. Labor
Count the hours for each task: prep, forming, rebar, the pour, finishing, and saw cuts. Then multiply by what an hour really costs you. That is more than the wage. It includes taxes and insurance too.
6. Add it up, then add margin
Total every cost. Then divide by 0.75 for a 25% margin. Don't multiply by 1.25. That only gets you 20%. See how to bid a concrete driveway for the full example.
Slab calculator
Let your phone do the takeoff.
SlabBid Pro figures the yards, rebar, and labor hours for you. It builds a material list you can text to your supplier. Then it sends the quote with your logo on it.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How much rebar for a slab · How much gravel under a slab · Concrete price per square foot