Most crews bid saw cuts by eye, or leave them off. A 24 × 20 driveway poured 4 inches thick needs 64 feet of cut. At an example $2 a foot, that is $128 you eat if it is not on the bid. Cut the joints too far apart and the slab picks its own places to crack. Here is how to figure where the cuts go and how many feet to bid.

Step 1: Find the most space between joints

The National Ready Mixed Concrete Association (NRMCA) says joints should be no more than 24 to 36 times the slab thickness apart, and never more than 15 feet. Their example: a 4 inch slab gets joints about 10 feet apart. Measure the thickness in inches and read the spacing in feet.

Slab thickness Joints at 24 to 36 times
4 inches 8 to 12 feet
5 inches 10 to 15 feet
6 inches 12 to 15 feet (18 is over the cap)

Step 2: Keep the panels close to square

Each panel between joints should be square or nearly so. NRMCA says the long side should not be more than 1.5 times the short side, and to avoid L-shaped panels. That means every inside corner of the slab needs a joint running out of it. A narrow walk gets joints about as far apart as it is wide, even if that is closer than the spacing in the table.

Step 3: Work an example

A 24 × 20 driveway, 4 inches thick. Using 2.5 times the thickness, the most space between joints is 10 feet.

24 ft ÷ 10 = 2.4, so 3 panels of 8 ft. That is 2 cuts.
20 ft ÷ 10 = 2, so 2 panels of 10 ft. That is 1 cut.

Each panel is 8 × 10 ft, six panels in all. The long side is 1.25 times the short side, under the 1.5 limit. Check: 6 panels × 80 sq ft = 480 sq ft, and 24 × 20 = 480.

Cuts across the width: 2 × 20 ft = 40 ft
Cut down the length: 1 × 24 ft = 24 ft
Total: 64 ft of saw cut

At an example $2 a foot, that is $128. Use your own rate, or your saw guy's price.

Step 4: Cut deep enough

NRMCA says the joint should be at least 1/4 of the slab thickness deep, and never less than 1 inch. A 4 inch slab gets a 1 inch cut. A 6 inch slab gets 1 1/2 inches.

Saw cut layout calculator

Most space between joints10 ft
Cuts across the width2
Cuts down the length1
Panels6
Panel size8 × 10 ft
Cut depth, at least1 in
Saw cut feet64 ft
Saw cut cost$128

Plain rectangles only. Check every measurement on the slab before you cut. Follow the plans or spec on the job if there is one.

What this does not cover

This is the rule of thumb for a plain rectangle. Round pads, curved drives, L and U shapes, isolation joints where the slab meets a wall or column, and anything thicker or heavily loaded can change the layout. When the job has plans or an engineer's joint layout, follow that.

Plan the saw cuts before you pour.

SlabBid Pro 1.5 has a saw-cut planner. Enter each side of the slab and it lays out the joints and checks every panel. You can set how many cuts go each way, move or lock a cut, get chalk-line measurements, and share a cut sheet with your crew. It puts the feet of cut on the bid. It does straight cuts on four kinds of slab, and it is a planning aid, so check it before you cut. Look through the sample jobs first, then try it free for 7 days.

Get SlabBid Pro on the App Store

Free for 7 days, then $9.99 a month or $99 a year. iPhone and iPad.

Source: NRMCA, Concrete in Practice CIP 6, Joints in Concrete Slabs on Grade.