How to Bid a Monolithic Slab With Thickened Edges

A monolithic slab is a floor and a footing poured at the same time. The edges are dug deeper to carry the walls. Some call it a mono slab or a thickened edge slab. Crews lose money on these when they bid the floor and forget the concrete in the edges. Here is how to bid one, using a 24 × 30 garage slab poured 4 inches thick with edges 12 inches wide and 12 inches deep.

Step 1: Figure the slab yards

24 × 30 = 720 square feet. Length × width × thickness in inches ÷ 12 ÷ 27 = cubic yards.

24 × 30 × 4 ÷ 12 ÷ 27 = 8.89 yards

That is the flat floor only. The edges come next.

Step 2: Figure the edge yards

The edge is 12 inches deep in all. The slab already covers 4 inches of that. So the extra is 8 inches deep and 12 inches wide. Measure all the way around: 24 + 30 + 24 + 30 = 108 feet.

108 × 12 ÷ 12 × 8 ÷ 12 ÷ 27 = 2.67 yards

Slab plus edges is 11.56 yards. Add 10% so you don't run short. That is 12.71 yards. Order 13.

Bid the floor alone and you would order 10 yards. The edges add 3 more. Skip them and you eat $510 of concrete at this price. The plans or your local code set the edge size and the steel. Bid what they call for.

Step 3: Add up every cost

These are example numbers. Use your own.

Cost Amount
Concrete, 13 yards at $170 $2,210
Gravel base, rebar, forms, vapor barrier $1,150
Labor, 4 men × 10 hours × $35 $1,400
Fuel, blades, saw cuts $125
Your total cost $4,885

Step 4: Watch for mono slab extras

  • Digging the edges. Somebody has to dig that trench and move the dirt. By hand or by machine, it is hours on your bid.
  • Sloped edges. Many edges slope back up to the slab instead of dropping straight. The slope takes more concrete. Add extra yards for it.
  • Frost. In cold places, the code may call for deeper edges or foam board. Check with the building office before you bid.
  • Edge steel and anchor bolts. The plans set the bars in the edge and the bolts for the walls. Count them. See how much rebar you need for a slab.
  • Taller forms. If the slab sits above grade, the outside forms are taller and need more stakes and bracing.
  • Thick spots inside. Posts and inside walls may need a thick pad under them. Figure each one like a small footing.

Step 5: Add your margin

To hit a 25% margin, divide your cost by 0.75.

$4,885 ÷ 0.75 = $6,513

You keep $1,628. That is $9.05 a square foot. It is more than a plain floor the same size because the edges add concrete, steel, and digging.

Monolithic slab bid calculator

Slab yards8.89 yd
Edge yards2.67 yd
Order (with 10% extra)13 yd
Your total cost$4,885
Price per square foot$9.05
Your bid$6,513

Price the slab and the edges in one bid.

SlabBid Pro adds up the slab, footings, rebar, gravel, digging, labor, and margin for you. Then it sends a clean quote with your logo by text or email.