A monolithic slab is a floor and a footing poured at the same time. The edges are dug deeper to carry the walls. Some call it a mono slab or a thickened edge slab. Crews lose money on these when they bid the floor and forget the concrete in the edges. Here is how to bid one, using a 24 × 30 garage slab poured 4 inches thick with edges 12 inches wide and 12 inches deep.
Step 1: Figure the slab yards
24 × 30 = 720 square feet. Length × width × thickness in inches ÷ 12 ÷ 27 = cubic yards.
24 × 30 × 4 ÷ 12 ÷ 27 = 8.89 yards
That is the flat floor only. The edges come next.
Step 2: Figure the edge yards
The edge is 12 inches deep in all. The slab already covers 4 inches of that. So the extra is 8 inches deep and 12 inches wide. Measure all the way around: 24 + 30 + 24 + 30 = 108 feet.
108 × 12 ÷ 12 × 8 ÷ 12 ÷ 27 = 2.67 yards
Slab plus edges is 11.56 yards. Add 10% so you don't run short. That is 12.71 yards. Order 13.
Bid the floor alone and you would order 10 yards. The edges add 3 more. Skip them and you eat $510 of concrete at this price. The plans or your local code set the edge size and the steel. Bid what they call for.
Step 3: Add up every cost
These are example numbers. Use your own.
| Cost | Amount |
|---|---|
| Concrete, 13 yards at $170 | $2,210 |
| Gravel base, rebar, forms, vapor barrier | $1,150 |
| Labor, 4 men × 10 hours × $35 | $1,400 |
| Fuel, blades, saw cuts | $125 |
| Your total cost | $4,885 |
Step 4: Watch for mono slab extras
- Digging the edges. Somebody has to dig that trench and move the dirt. By hand or by machine, it is hours on your bid.
- Sloped edges. Many edges slope back up to the slab instead of dropping straight. The slope takes more concrete. Add extra yards for it.
- Frost. In cold places, the code may call for deeper edges or foam board. Check with the building office before you bid.
- Edge steel and anchor bolts. The plans set the bars in the edge and the bolts for the walls. Count them. See how much rebar you need for a slab.
- Taller forms. If the slab sits above grade, the outside forms are taller and need more stakes and bracing.
- Thick spots inside. Posts and inside walls may need a thick pad under them. Figure each one like a small footing.
Step 5: Add your margin
To hit a 25% margin, divide your cost by 0.75.
$4,885 ÷ 0.75 = $6,513
You keep $1,628. That is $9.05 a square foot. It is more than a plain floor the same size because the edges add concrete, steel, and digging.
Monolithic slab bid calculator
Price the slab and the edges in one bid.
SlabBid Pro adds up the slab, footings, rebar, gravel, digging, labor, and margin for you. Then it sends a clean quote with your logo by text or email.