Tear-out is where a lot of bids leak money. Old concrete is heavy, it takes up more room once it's broken, and the dump charges by weight. Here is how to price it, using an old 20 × 24 slab, 4 inches thick.
Step 1: Check the real thickness
Don't trust what the owner tells you. Look at an edge or drill a test hole. Old slabs are often thicker at the edges, and some have rebar or mesh, which slows the break-up.
Step 2: Figure the weight
Normal concrete weighs about 150 pounds per cubic foot. That is about 2 tons per cubic yard.
20 × 24 × 0.333 = 160 cubic feet = 5.93 yards
160 × 150 = 24,000 pounds = 12 tons
Step 3: Figure your haul
Broken concrete takes more room than solid. A rule of thumb is about half again as much.
5.93 × 1.5 = about 8.9 loose yards
Count your trips by your truck's weight limit, not the size of the box. Concrete gets too heavy long before the box is full.
Step 4: Add up the cost
These are example numbers. Use your own.
| Cost | Amount |
|---|---|
| Dump fee, 12 tons at $30 | $360 |
| Labor, 3 men × 6 hours × $35 | $630 |
| Skid steer and breaker rental | $400 |
| Your total cost | $1,390 |
That is $2.90 a square foot in cost. At a 25% margin, $1,390 ÷ 0.75 = $1,853, or about $3.86 a square foot.
Some recyclers take clean concrete for less than the dump, or even free. Call around. It can be the cheapest line on the job to fix.
Tear-out calculator
Never forget the tear-out again.
SlabBid Pro has tear-out built into every bid, right next to the concrete, rebar, labor, and margin. Then it sends a clean quote with your logo by text or email.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to bid a concrete driveway · How to bid a concrete patio · How to figure concrete labor cost