Order too little and you're stuck with a cold joint and a second truck. Order too much and you pay for concrete you dump. Here is how to get the yards right for the shapes you pour most.
The one rule
Get every size in feet. Multiply to get cubic feet. Divide by 27 to get cubic yards. To change inches to feet, divide by 12.
Slabs
Length × width × (thickness ÷ 12) ÷ 27
A 20 × 20 slab, 4 inches thick: 20 × 20 × 0.333 ÷ 27 = 4.94 yards.
| Slab thickness | Yards per 100 sq ft |
|---|---|
| 4 inches | 1.23 |
| 5 inches | 1.54 |
| 6 inches | 1.85 |
Footings
Length × (width ÷ 12) × (depth ÷ 12) ÷ 27
See how to estimate concrete footings for a full example.
Round piers and tubes
3.14 × radius × radius × depth ÷ 27
The radius is half the width, in feet. A 12-inch tube has a 0.5-foot radius. At 4 feet deep: 3.14 × 0.5 × 0.5 × 4 = 3.14 cubic feet, or 0.116 yards. Ten of them is 1.16 yards.
How much extra to order
Add about 10%. Forms bow, the ground is never flat, and some always stays in the chute and the pump. Add more when you pour into dug dirt, over a low subgrade, or into rough forms.
Ask your plant how they sell it. Many sell in quarter or half yards, and many charge a fee for small orders. Knowing that before the pour can save a second truck.
Yardage calculator
Slab
Round piers
Only need one? Set the other to 0.
Get the yards and the whole bid.
SlabBid Pro figures the yards for slabs, footings, and walls, then adds rebar, labor, and margin. It even builds a material list you can text to your supplier.
Get SlabBid Pro on the App StoreFree for 7 days. iPhone and iPad.
More guides: How to estimate a concrete slab · How to estimate concrete footings · Concrete price per square foot