How to Bid a Concrete Sidewalk

A sidewalk is long and skinny. That means few yards, but lots of form boards, lots of joints, and lots of edge to finish. Here is how to bid one, using a walk 60 feet long, 4 feet wide, and 4 inches thick.

Step 1: Figure your yards

60 × 4 = 240 square feet. Length × width × thickness (in feet) ÷ 27 = cubic yards.

60 × 4 × 0.333 ÷ 27 = 2.96 yards

Add 10% so you don't run short. That is 3.26 yards. Order 4. A job this small will likely carry a short-load fee, so ask your plant.

Step 2: Count your forms

Form both long sides and both ends.

(60 × 2) + (4 × 2) = 128 feet of form

Add stakes about every 3 to 4 feet, more on curves. A curved walk takes bendable form and more time to set.

Step 3: Plan your control joints

Joints tell the concrete where to crack. On sidewalks, many crews put a joint at a spacing close to the width of the walk. A 4-foot walk gets a joint every 4 feet.

60 ÷ 4 = 15 panels, so 14 joints

Tooled joints add finishing time. Saw cuts add a blade and a trip back. Either way, count them.

Step 4: Price the hidden work

  • Grade work. A long walk often needs dirt cut or filled to keep it smooth and draining.
  • Tear-out. Old walk has to be broken up and hauled. See how to price concrete tear-out.
  • Tie-ins. Meeting a driveway, steps, or a city walk may need dowels or an expansion joint.
  • Permits. Walks along a street may need a city permit and a set thickness. Check first.
  • Access. A walk along the side of a house may be out of chute reach.

Then add up every cost and divide by 0.75 for a 25% margin. See markup vs margin for why.

Sidewalk calculator

Square feet240
Exact yards2.96 yd
Form boards128 ft
Control joints14
Order (with 10% extra)4 yd

Bid the walk on your phone.

SlabBid Pro figures the yards, forms, joints, and labor for you. Then it sends a clean quote with your logo by text or email.

Get SlabBid Pro on the App Store

Free for 7 days. iPhone and iPad.

More guides: How to bid a concrete patio · How to bid a concrete driveway · How many yards of concrete do I need