How to Price Winter Concrete: Blankets, Hot Water, and Accelerator

Cold weather makes every pour cost more. Hot water, accelerator, blankets, and extra hours all add up. If they are not in the bid, they come out of your pocket. Here is how to price them, using a 24 × 24 garage slab poured 4 inches thick.

Step 1: Figure your yards

Most winter charges from the plant are priced per yard. So start with the yards. 24 × 24 = 576 square feet. Square feet × thickness in inches ÷ 12 ÷ 27 = cubic yards. The plans or local code decide the thickness.

576 × 4 ÷ 12 ÷ 27 = 7.11 yards

Add 10% so you don't run short. That is 7.82 yards. Order 8.

Step 2: Add up every winter cost

These are example numbers. Use your own. Call your plant and ask what they charge in winter.

Winter cost Amount
Hot water, 8 yards at $8 $64
Accelerator, 8 yards at $12 $96
Blankets, 5 at $15 each for wear $75
Heater and fuel to thaw the ground $120
Extra labor, 8 hours × $35 $280
Your total winter cost $635

The 8 extra hours are 3 men staying 2 hours longer on pour day, plus 1 man for 2 hours to come back and pull the blankets.

Step 3: Watch for winter extras

  • Frozen ground. Do not pour on frozen ground. Thawing it takes heat, blankets, and a day or more. Somebody has to pay for that.
  • Steel in the slab. Some plans do not allow certain accelerators with rebar or mesh. The plans or local code decide. Ask your plant what they offer.
  • Slow set. Cold concrete takes longer to finish. Your crew may be there after dark. Bid lights and the extra hours.
  • Blanket days. The plans or local code decide how long the slab stays covered. More days means more trips.
  • Short days. You get less daylight. A job that takes one day in summer may take two.
  • Small loads. Winter charges stack on top of short-load fees. See concrete short-load fees.
  • Put it in writing. Show winter protection as its own line on the quote. Then the customer sees why the price is higher.

Step 4: Add your margin

Winter costs get the same margin as the rest of the job. To hit a 25% margin, divide your cost by 0.75.

$635 ÷ 0.75 = $847

You keep $212. That adds $1.47 a square foot to this slab. Add the $847 on top of your normal bid for the job.

Winter concrete cost calculator

Order (with 10% extra)8 yd
Plant winter charges$160
Extra labor$280
Your total winter cost$635
Added per square foot$1.47
Add to your bid$847

Price the job before you leave the site.

SlabBid Pro figures the concrete, rebar, base, labor, and margin from your measurements. Then it sends a clean quote with your logo by text or email.

Get SlabBid Pro on the App Store

Free for 7 days. iPhone and iPad.

More guides: How to bid a concrete garage floor · How to bid a basement floor · How to figure concrete labor cost